Question 1 of 20Transformers & generators
PUT IT INTO PRACTICE

A single-phase transformer steps 7,200 V down to 240 V. The secondary load draws 90 A. Ignoring losses, how much current flows in the primary?

Given conditions

Ideal transformer, no losses

Select your answer
Report a problem with this question

Describe the content issue. Do not include private patient or workplace information.

Pick an answer and check it.

See all 20 questions with answers and explanations
  1. A single-phase transformer steps 7,200 V down to 240 V. The secondary load draws 90 A. Ignoring losses, how much current flows in the primary?

    • 1.5 A
    • 3.0 A
    • 90.0 A
    • 2,700.0 A

    Answer: 3.0 A

    Why: The turns ratio equals the voltage ratio: 7,200 ÷ 240 = 30. Current changes the opposite way to voltage, so the primary carries 90 ÷ 30 = 3 A. Check: 7,200 × 3 = 21,600 VA and 240 × 90 = 21,600 VA.

  2. A loose splice on a branch circuit has 0.05 Ω of resistance and carries 40 A. How much power is turned into heat at the splice?

    • 2 W
    • 80 W
    • 800 W
    • 1,600 W

    Answer: 80 W

    Why: With amps and ohms given, use P = I² × R: 40² × 0.05 = 1,600 × 0.05 = 80 W. That is a small lamp's worth of heat buried in a box. Because heat rises with the square of current, a bad termination that is fine at light load can scorch at heavy load.

  3. In which installation is the next-size-up allowance of 240.4(B) NOT permitted?

    • A multioutlet receptacle branch circuit for portable loads
    • A feeder with 140 A ampacity protected by a 150 A breaker
    • An individual branch circuit to one fixed appliance
    • A feeder with 475 A ampacity protected at 500 A

    Answer: A multioutlet receptacle branch circuit for portable loads

    Why: 240.4(B)(1) excludes branch circuits that supply more than one receptacle for cord-and-plug-connected portable loads. Any plug on that circuit could draw up to the breaker rating, so the breaker must not exceed the conductor ampacity. (NEC 240.4(B)(1))

  4. Article 100 defines a continuous load as one where the maximum current is expected to continue for how long?

    • 30 minutes or more
    • 1 hour or more
    • 2 hours or more
    • 3 hours or more

    Answer: 3 hours or more

    Why: Article 100 defines a continuous load as a load where the maximum current is expected to continue for 3 hours or more. Store lighting, office lighting and EV charging are typical examples. (NEC Article 100 (Continuous Load))

  5. Under the 2023 NEC, a one-family dwelling has 1,800 ft² of living space (outside dimensions), a 400 ft² attached garage, and a 200 ft² open front porch. Using the standard method, what is the general lighting load before any demand factor?

    • 5,400 VA
    • 6,000 VA
    • 6,600 VA
    • 7,200 VA

    Answer: 5,400 VA

    Why: 220.41 assigns 3 VA per square foot to dwelling units, but 220.5(C) counts only floor area that is, or can become, living space, measured from outside dimensions. Garages, open porches, and unfinished space not adaptable for future use are left out. 1,800 ft² × 3 VA = 5,400 VA. (NEC 220.5(C), 220.41) Edition note: 2023 NEC numbering. In the 2026 NEC, load calculations moved from Article 220 to Article 120. In the 2020 NEC the 3 VA/ft² dwelling load was in 220.14(J) and floor area in 220.11.

  6. Under 90.3, which chapters of the NEC apply generally to all electrical installations?

    • Chapters 1 through 7
    • Chapters 1 through 3
    • Chapters 1 through 9
    • Chapters 1 through 4

    Answer: Chapters 1 through 4

    Why: Section 90.3 says Chapters 1 through 4 apply generally. Chapters 5, 6 and 7 apply to special occupancies, special equipment and special conditions and may supplement or modify the general rules. Knowing this split tells you where to look first. (NEC 90.3)

  7. The general lighting in a retail store runs at full load from 8 a.m. to 10 p.m. every day. Under Article 100, how is this load classified?

    • Noncontinuous load
    • Intermittent duty
    • Periodic duty
    • Continuous load

    Answer: Continuous load

    Why: Article 100 defines a continuous load as one where maximum current is expected to continue for 3 hours or more. Store lighting that runs all day easily qualifies, so it gets the 125 % sizing rules for conductors and overcurrent devices. (NEC Article 100, Continuous Load)

  8. Along an unbroken living room wall, what is the maximum distance from any point on the floor line to the nearest receptacle outlet?

    • 4 ft
    • 6 ft
    • 10 ft
    • 12 ft

    Answer: 6 ft

    Why: 210.52(A)(1) requires receptacles placed so that no point along the floor line of any wall space is more than 6 ft from a receptacle outlet. That allows receptacles up to 12 ft apart. (NEC 210.52(A)(1))

  9. A 120 V ungrounded conductor faults to a metal sign whose only connection to anything is a ground rod. The total path through the earth back to the utility's grounded conductor measures 25 Ω, and the circuit breaker is rated 20 A. Ignoring wire resistance, about how much fault current flows?

    • 0.21 A
    • 4.8 A
    • 20 A
    • 3,000 A

    Answer: 4.8 A

    Why: Ohm's law: I = E ÷ R = 120 V ÷ 25 Ω = 4.8 A. That's far below the breaker's 20 A rating, so the breaker never trips and the sign stays energized. This is exactly why 250.4(A)(5) says the earth can't be the effective ground-fault current path. (NEC 250.4(A)(5))

  10. You're setting a feeder-supplied panelboard in the same building as the service. The feeder has two ungrounded conductors, a neutral, and an EGC. The panel ships with a green bonding screw for the neutral bar. What do you do with the screw?

    • Install it so the neutral bar is bonded to the can
    • Install it, but only if a ground rod is added here
    • Install it, but only if the feeder lacks an EGC
    • Leave it out and keep the neutral bar isolated

    Answer: Leave it out and keep the neutral bar isolated

    Why: Past the service disconnect, the grounded conductor may not be connected to equipment grounding (250.24(A)(5), 250.142(B)). The neutral bar stays isolated, and the EGCs land on a separate equipment grounding bar bonded to the enclosure (408.40). The only neutral-to-ground bond is the main bonding jumper at the service. (NEC 250.24(A)(5), 250.142(B), 408.40)

  11. A branch circuit supplies 36 A of continuous load and 8 A of noncontinuous load. The breaker is not listed for 100 % operation. What is the minimum standard breaker rating?

    • 40 A
    • 45 A
    • 50 A
    • 60 A

    Answer: 60 A

    Why: 210.20(A): at least 125 % of the continuous load plus 100 % of the noncontinuous load. 36 × 1.25 = 45 A, plus 8 A = 53 A. The next standard rating at or above 53 A is 60 A. (NEC 210.20(A), 240.6(A))

  12. A 75 kVA, three-phase, 480 V to 208Y/120 V transformer is protected on the primary side only. What is the largest standard primary breaker permitted by Table 450.3(B) and its notes?

    • 90 A
    • 100 A
    • 110 A
    • 125 A

    Answer: 125 A

    Why: Primary current is 75,000 ÷ (1.732 × 480) = 90.21 A. Primary-only protection for 9 A or more is 125 %: 90.21 × 1.25 = 112.77 A. Table 450.3(B) Note 1 permits the next higher standard size, 125 A. (NEC 450.3(B), Table 450.3(B), 240.6(A))

  13. A 2 hp, 115 V, single-phase motor drives a shop air compressor (not a hermetic refrigerant compressor). What minimum ampacity must its branch-circuit conductors have?

    • 15.0 A
    • 24.0 A
    • 27.6 A
    • 30.0 A

    Answer: 30.0 A

    Why: Single-phase motors use Table 430.248, which lists 24 A for 2 hp at 115 V. 430.22 requires 125 %: 24 × 1.25 = 30 A. (NEC Table 430.248, 430.22)

  14. A single PV string uses modules with a short-circuit current (Isc) of 9.6 A. Using the 125 % method, what is the maximum circuit current for this string? (Round to two decimals.)

    • 9.60 A
    • 11.04 A
    • 12.00 A
    • 15.00 A

    Answer: 12.00 A

    Why: 690.8(A)(1) sets the maximum current of a PV string at 125 % of the module Isc. The extra 25 % covers sunlight stronger than the standard test condition, such as cold, clear days with reflected light. 9.6 A × 1.25 = 12.00 A. A second 125 % is applied later, when you size conductors and overcurrent devices. (NEC 690.8(A)(1))

  15. A 4,500 W water heater element runs 3 hours a day for 30 days. Electricity costs $0.15 per kWh. What is the energy cost for the month?

    • $2.03
    • $20.25
    • $60.75
    • $60,750

    Answer: $60.75

    Why: Energy is power × time, billed in kilowatt-hours. Convert to kW first: 4,500 W = 4.5 kW. Energy = 4.5 kW × 3 h × 30 days = 405 kWh. Cost = 405 × $0.15 = $60.75.

  16. A resistive heater is moved from a 120 V circuit to a 240 V circuit. If its resistance stays the same, how does its power compare with before?

    • One-quarter as much
    • One-half as much
    • Twice as much
    • Four times as much

    Answer: Four times as much

    Why: With resistance fixed, P = E² ÷ R. Doubling E makes E² four times larger, so the heater makes four times the watts. Current doubles too (I = E ÷ R), and twice the volts times twice the amps is four times the power. That is why a 120 V heater on 240 V fails fast.

  17. A section says a wiring method 'shall be permitted' in a certain location. Under 90.5, what does that language mean?

    • The method is allowed but not required
    • The method is required in that location
    • The method needs special permission first
    • The text is explanatory and not enforceable

    Answer: The method is allowed but not required

    Why: Section 90.5 sorts code text into mandatory rules ('shall', 'shall not'), permissive rules ('shall be permitted', 'shall not be required') and explanatory material. A permissive rule allows an action without demanding it, so you may use the method but are not forced to. (NEC 90.5(A), 90.5(B))

  18. You need the requirements for a rooftop solar photovoltaic system (Article 690). Which chapter of the NEC contains it?

    • Chapter 5
    • Chapter 6
    • Chapter 7
    • Chapter 8

    Answer: Chapter 6

    Why: Chapter 6 covers special equipment, including signs, elevators, EV charging, pools (680) and solar PV (690). The first digit of the article number is the chapter: 690 is in Chapter 6. (NEC Article 690, 90.3)

  19. A new in-ground pool is installed at a single-family home. At least one 125 V, 15 or 20 A general-purpose receptacle is required near the pool. Between what distances from the inside wall of the pool must it be located?

    • 5 ft and 10 ft
    • 5 ft and 20 ft
    • 6 ft and 10 ft
    • 6 ft and 20 ft

    Answer: 6 ft and 20 ft

    Why: 680.22(A)(1) requires at least one general-purpose receptacle at a dwelling pool so nobody runs an extension cord across the deck. It must sit no closer than 6 ft and no farther than 20 ft from the inside wall, and no higher than 6 ft 6 in. above the deck. It is also GFCI protected because it is within 20 ft. (NEC 680.22(A)(1))

  20. A 120 V branch circuit supplies a metal pole light in a parking lot. Which of these must not be counted on as the effective ground-fault current path for that circuit?

    • The earth, through a ground rod at the pole
    • An EMT raceway with listed set-screw fittings
    • A copper wire-type equipment grounding conductor
    • The metal armor of listed Type AC cable

    Answer: The earth, through a ground rod at the pole

    Why: 250.4(A)(5) says the earth is not to be considered an effective ground-fault current path. Soil resistance is far too high to let enough current flow to open the breaker. The fault path has to be an intentional, low-impedance metal path back to the source, such as EMT, a wire-type EGC, or AC cable armor, all of which 250.118 permits. (NEC 250.4(A)(5), 250.118)