West Virginia Journeyman Electrician Practice Test
20 questions in the style of the West Virginia journeyman exam (State-run): NEC rules, code navigation and calculations. Pick an answer, check it, and read why — with the section to look up.
The supply frequency to a circuit rises from 50 Hz to 60 Hz. What happens to inductive reactance (XL) and capacitive reactance (XC)?
Report a problem with this question
See all 20 questions with answers and explanations
The supply frequency to a circuit rises from 50 Hz to 60 Hz. What happens to inductive reactance (XL) and capacitive reactance (XC)?
- XL rises and XC rises
- XL falls and XC rises
- XL falls and XC falls
- XL rises and XC falls
Answer: XL rises and XC falls
Why: XL = 2πfL, so it rises in step with frequency. XC = 1 ÷ (2πfC), so frequency is in the denominator and XC falls as frequency rises. Coils fight fast changes harder; capacitors pass them more easily.
Five THHN conductors will be installed in a 60 ft run of EMT between two panelboards. What maximum percentage of the EMT's cross-sectional area may the conductors fill?
- 31 %
- 40 %
- 53 %
- 60 %
Answer: 40 %
Why: Chapter 9, Table 1 allows 40 % fill when a raceway holds more than two conductors. 53 % is for one conductor, 31 % for two, and 60 % only for nipples 24 in. or shorter. A 60 ft run is a full raceway, so 40 % applies. (NEC Chapter 9, Table 1)
You are pouring a 1-1/2 in. trade size sealing fitting in a Class I, Division 1 location. The fitting has no marking that calls for a different depth. What is the minimum thickness of sealing compound?
- 5/8 in.
- 3/4 in.
- 1-1/2 in.
- 2 in.
Answer: 1-1/2 in.
Why: The compound must be at least as thick as the trade size of the sealing fitting, and never less than 5/8 in. (501.15(C)(3)). For a 1-1/2 in. fitting that means at least 1-1/2 in. of compound. The 5/8 in. figure is only the floor for very small fittings. (NEC 501.15(C)(3))
A 25 kVA, single-phase transformer has a 480 V primary and a 240 V secondary. What is its full-load secondary current?
- 52.08 A
- 60.14 A
- 104.17 A
- 180.42 A
Answer: 104.17 A
Why: Single-phase current is VA ÷ volts, with no √3. On the 240 V side: 25,000 ÷ 240 = 104.17 A. The secondary current is twice the primary current because the voltage is half.
Under the 2023 NEC standard method, a 2,400 ft² dwelling has the two required small-appliance circuits and one laundry circuit. What is the net general lighting, small-appliance and laundry demand after Table 220.45?
- 4,095 VA
- 5,520 VA
- 6,045 VA
- 11,700 VA
Answer: 6,045 VA
Why: Start with 2,400 × 3 VA = 7,200 VA, then add 1,500 VA for each small-appliance and laundry circuit (220.52): 7,200 + 3,000 + 1,500 = 11,700 VA. Table 220.45 takes the first 3,000 VA at 100 % and the next portion, up to 120,000 VA, at 35 %: 3,000 + (8,700 × 0.35) = 6,045 VA. (NEC 220.41, 220.52(A), 220.52(B), Table 220.45) Edition note: 2023 NEC numbering. In the 2026 NEC, load calculations moved from Article 220 to Article 120. The dwelling demand tiers were Table 220.42 in the 2020 NEC and are Table 220.45 in 2023.
A 120 V ungrounded conductor faults to a metal sign whose only connection to anything is a ground rod. The total path through the earth back to the utility's grounded conductor measures 25 Ω, and the circuit breaker is rated 20 A. Ignoring wire resistance, about how much fault current flows?
- 0.21 A
- 4.8 A
- 20 A
- 3,000 A
Answer: 4.8 A
Why: Ohm's law: I = E ÷ R = 120 V ÷ 25 Ω = 4.8 A. That's far below the breaker's 20 A rating, so the breaker never trips and the sign stays energized. This is exactly why 250.4(A)(5) says the earth can't be the effective ground-fault current path. (NEC 250.4(A)(5))
You're setting a feeder-supplied panelboard in the same building as the service. The feeder has two ungrounded conductors, a neutral, and an EGC. The panel ships with a green bonding screw for the neutral bar. What do you do with the screw?
- Install it so the neutral bar is bonded to the can
- Install it, but only if a ground rod is added here
- Install it, but only if the feeder lacks an EGC
- Leave it out and keep the neutral bar isolated
Answer: Leave it out and keep the neutral bar isolated
Why: Past the service disconnect, the grounded conductor may not be connected to equipment grounding (250.24(A)(5), 250.142(B)). The neutral bar stays isolated, and the EGCs land on a separate equipment grounding bar bonded to the enclosure (408.40). The only neutral-to-ground bond is the main bonding jumper at the service. (NEC 250.24(A)(5), 250.142(B), 408.40)
A branch circuit supplies 36 A of continuous load and 8 A of noncontinuous load. The breaker is not listed for 100 % operation. What is the minimum standard breaker rating?
- 40 A
- 45 A
- 50 A
- 60 A
Answer: 60 A
Why: 210.20(A): at least 125 % of the continuous load plus 100 % of the noncontinuous load. 36 × 1.25 = 45 A, plus 8 A = 53 A. The next standard rating at or above 53 A is 60 A. (NEC 210.20(A), 240.6(A))
In which installation is the next-size-up allowance of 240.4(B) NOT permitted?
- A multioutlet receptacle branch circuit for portable loads
- A feeder with 140 A ampacity protected by a 150 A breaker
- An individual branch circuit to one fixed appliance
- A feeder with 475 A ampacity protected at 500 A
Answer: A multioutlet receptacle branch circuit for portable loads
Why: 240.4(B)(1) excludes branch circuits that supply more than one receptacle for cord-and-plug-connected portable loads. Any plug on that circuit could draw up to the breaker rating, so the breaker must not exceed the conductor ampacity. (NEC 240.4(B)(1))
In a purely capacitive AC circuit, how does the current relate to the voltage?
- It lags the voltage by 90°
- It is in phase with the voltage
- It lags the voltage by 45°
- It leads the voltage by 90°
Answer: It leads the voltage by 90°
Why: A capacitor's current is greatest when the voltage is changing fastest, a quarter-cycle before the voltage peaks. So current leads voltage by 90°. Memory aid: ELI the ICE man. In C, I comes before E.
Three 6 AWG THHN copper current-carrying conductors run through a boiler room with a 45 °C ambient. Using Table 310.15(B)(1)(1), what is the conductor's ampacity after ambient correction, before the termination check?
- 53.30 A
- 60.00 A
- 61.50 A
- 65.25 A
Answer: 65.25 A
Why: THHN is 90 °C, so start at 75 A (6 AWG copper, 90 °C column). The 41–45 °C row gives 0.87 in the 90 °C column: 75 × 0.87 = 65.25 A. The 110.14(C) termination check comes afterwards. (NEC Table 310.15(B)(1)(1), Table 310.16) Edition note: The 2023 NEC numbers the 30 °C-based correction table as Table 310.15(B)(1)(1); the 2020 edition called it Table 310.15(B)(1).
Under the 2023 NEC, a one-family dwelling has 1,800 ft² of living space (outside dimensions), a 400 ft² attached garage, and a 200 ft² open front porch. Using the standard method, what is the general lighting load before any demand factor?
- 5,400 VA
- 6,000 VA
- 6,600 VA
- 7,200 VA
Answer: 5,400 VA
Why: 220.41 assigns 3 VA per square foot to dwelling units, but 220.5(C) counts only floor area that is, or can become, living space, measured from outside dimensions. Garages, open porches, and unfinished space not adaptable for future use are left out. 1,800 ft² × 3 VA = 5,400 VA. (NEC 220.5(C), 220.41) Edition note: 2023 NEC numbering. In the 2026 NEC, load calculations moved from Article 220 to Article 120. In the 2020 NEC the 3 VA/ft² dwelling load was in 220.14(J) and floor area in 220.11.
A feeder supplies 90 A of continuous lighting load and no other load. The breaker is not listed for 100 % operation. What is the minimum standard breaker rating?
- 90 A
- 110 A
- 125 A
- 150 A
Answer: 125 A
Why: 215.3 requires the feeder overcurrent device to be at least 125 % of the continuous load: 90 × 1.25 = 112.5 A. 112.5 A isn't a standard rating, so go up to the next standard size in 240.6(A), 125 A. (NEC 215.3, 240.6(A))
Under the 2023 NEC standard method, a 2,000 ft² one-family dwelling on a 120/240 V service has 2 small-appliance circuits, 1 laundry circuit, a 12 kW range, a 5 kW dryer, four fastened-in-place appliances totaling 8,100 VA, 10 kW of fixed electric heat, and a 6 kVA air conditioner. What is the calculated load in amperes?
- 128 A
- 130 A
- 136 A
- 145 A
Answer: 145 A
Why: General load: 6,000 + 3,000 + 1,500 = 10,500 VA, reduced by Table 220.45 to 3,000 + (7,500 × 0.35) = 5,625 VA. Add the range at 8,000 VA (Table 220.55, Column C), the dryer at 5,000 VA (220.54), the appliances at 8,100 × 0.75 = 6,075 VA (220.53), and the larger of heat or AC, 10,000 VA (220.51, 220.60). Total 34,700 VA ÷ 240 V = 144.58 A, which rounds to 145 A (220.5(B)). (NEC Table 220.45, 220.51, 220.53, 220.54, Table 220.55, 220.60, 220.5(B)) Edition note: 2023 NEC numbering. In the 2026 NEC, load calculations moved from Article 220 to Article 120. The dwelling demand tiers were Table 220.42 in the 2020 NEC and are Table 220.45 in 2023.
Along an unbroken living room wall, what is the maximum distance from any point on the floor line to the nearest receptacle outlet?
- 4 ft
- 6 ft
- 10 ft
- 12 ft
Answer: 6 ft
Why: 210.52(A)(1) requires receptacles placed so that no point along the floor line of any wall space is more than 6 ft from a receptacle outlet. That allows receptacles up to 12 ft apart. (NEC 210.52(A)(1))
A textile mill has looms that throw off cotton lint and flyings, which collect on ledges and equipment. Under Article 500, how is this area classified?
- Class I, Group D
- Class II, Group G
- Class III
- Class II, Group E
Answer: Class III
Why: Class locations are sorted by what can burn. Class I is gases and vapors, Class II is combustible dust, and Class III is easily ignitible fibers and flyings such as cotton lint. Textile mills and cotton gins are the textbook Class III examples in 500.5(D). Class III has no material groups. (NEC 500.5(D))
An office building has an emergency system for egress lighting required by the building code. After normal power fails, within what time must the emergency system supply power?
- 10 seconds
- 30 seconds
- 60 seconds
- 90 seconds
Answer: 10 seconds
Why: 700.12 requires emergency lighting and power to be available within the time needed for the application, but no more than 10 seconds. Emergency systems protect life during evacuation, so people cannot be left in the dark for long. Legally required standby gets 60 seconds; optional standby has no time limit. (NEC 700.12)
A box with internal clamps contains two 12/2 NM cables spliced through for a 20 A circuit and one 14/2 NM cable feeding a 15 A duplex receptacle in the same box. All three cables have bare grounds. What minimum box volume is required?
- 21.50 in.³
- 22.00 in.³
- 23.50 in.³
- 24.00 in.³
Answer: 21.50 in.³
Why: Each conductor counts at its own size: 4 × 2.25 = 9.00 plus 2 × 2.00 = 4.00. Grounds take one allowance at the largest ground (12 AWG, 2.25) and clamps one at the largest conductor (12 AWG, 2.25). The receptacle is connected only to 14 AWG, so it takes 2 × 2.00 = 4.00 (314.16(B)(4)). Total 21.50 in.³. (NEC 314.16(B)(2), 314.16(B)(4), 314.16(B)(5), Table 314.16(B))
A 22 kW, 240 V, single-phase standby generator is rated at unity power factor. What minimum ampacity must the conductors from its output terminals to the first overcurrent device have?
- 60.9 A
- 91.7 A
- 105.4 A
- 114.6 A
Answer: 105.4 A
Why: Rated current is 22,000 ÷ 240 = 91.67 A. 445.13(A) requires these conductors to be rated at least 115 % of the nameplate current: 91.67 × 1.15 = 105.42 A, about 105.4 A. (NEC 445.13(A))
A one-family dwelling has a 125 A, 120/240 V, single-phase service supplying the entire dwelling load. Using 310.12 with copper THWN-2 conductors, 75 °C terminations, and no adjustment or correction factors, what is the minimum ungrounded service-entrance conductor size?
- 3 AWG
- 2 AWG
- 1 AWG
- 1/0 AWG
Answer: 2 AWG
Why: 310.12 lets the conductors of a 120/240 V single-phase dwelling service be sized at 83 % of the service rating: 125 × 0.83 = 103.75 A. In the 75 °C copper column of Table 310.16, 3 AWG is 100 A (too small) and 2 AWG is 115 A. So 2 AWG copper is the minimum. (NEC 310.12, Table 310.16)
Original practice questions written for Ohmward on the 2023 NEC — not real exam items.